Abstract:
Road construction project is the challenging process which needs huge manpower,
machineries and technical as well as financial capacity. Construction projects in
crowded urban road have faced different challenge to implement the road construction
such as high-traffic volume, utility conflicts and relocations and complex right-of-way
challenges of urban area construction. Therefore,the main objective of this study was to
assess the major challenges of the selectedon ongoing road constructionprojects in the
case of Addis Ababa city.
Descriptive and explanatory study methods were carried for this research in order to
achieve the objective of the study. Firstly, Guide lines (checklist) for the case study were
prepared. It contains the basic information about the selected road construction projects
such as: identify the major challenges that observed during the construction
implementation process, determining the challenges that influence on road
construction.Secondly, the research was conducted by identification of the major
challenges through literature review, desk study and site observation on selected road
projects. Based on this, the questionnaires were developed and distributed to
respondents to collect data from the relevant population (i.e. Client, contractors
andconsultants). Thirdly, evaluate the perception of different stakeholders on the issues
of the challenges and ranking of the variables. Finally,evaluation of roads was done by
checking compliance with the existing construction standards. Upon obtaining the
desired data, checking and organization of data has been done. This was followed by
thorough discussions in order to draw a conclusion and to forward recommendations
based on the findings of the study.
The distributed questioners to respondents were 100% returnedeven though, 73% of the
questioners were only valid. From result that obtained, elevenmajor challenges (i.e.right
of way problem, utility conflict, schedule constraints, variation order and poor project
management, Scarcity of material and financial, high traffic problem, performance of
stakeholders, poor public awareness, Design/poor planning and Environmental
factors)were identified from the selected road projects by using checklist; however, the
highest major challenge was right of way problem. On other hand, Time over run, Budget
over run, Creating social problem, Reduce work motivation, Dispute between parties,
Project termination and Leadership removal were identified as the most common and
recurrent effects of the challenges on the on-going road construction projects. All most
all the selected on-going road projects were not compliance with the standard.
Moreover, it is recommended that client should be facilitating timely compensation for
the property owners on the right of way of the road. Consultants should provide
completed project design where variation order will be negligible. Contractors should
follow the standards; Stakeholders need to build strong team to minimize lack of
coordination between organizations.