Abstract:
Infrastructure development, especially road building, is a key component in the development
of economies and links between cities. However, delays and cost overruns are persistent
problems in construction projects worldwide, particularly in developing regions where
institutional constraints, contractor capacity limitations and supply chain inefficiencies impact
construction project performance. In Somaliland, especially in Hargeisa District, road
building projects on a regular basis face delays and budget increases, but very limited
empirical research has been conducted on the interplay between several delay factors in the
context of road construction. This study used Partial Least Squares Structural Equation
Modeling (PLS-SEM) to analyze the relationships between key areas of delay and project
performance outcomes. A quantitative design was used and data were collected using
structured questionnaires from 300 professionals involved in road construction projects.
SmartPLS 4 was used to assess measurement reliability and structural relationships. The
results show that Project Management Performance significantly influences Construction Time
and Cost Overruns (β = 0.519, p < 0.001) and Construction Time and Cost Overruns are
significantly related to Quality and Stakeholder Satisfaction (β = 0.585, p < 0.001). Contractor,
stakeholder, supply chain, environmental, and external factors were also significantly
associated with Project Management Performance. The model accounts for 58.3% of the
variance in Project Management Performance, 26.9% in Construction Time and Cost
Overruns, and 54.2% in Quality and Stakeholder Satisfaction. Although the results offer
meaningful empirical insights, the study is based on perception data collected at a single point
in time in a single geographical context, which does not allow for strict causal interpretation
and broader generalization.