Abstract:
This paper considers the management of materials in building construction in Addis Ababa
housing construction projects. Construction industry has complexity in its nature because it
contains large number of parties as owners, consultants, contractors, stakeholders and micro
and small enterprises. Material management was a process of planning, executing and
controlling field and office activities in housing construction projects.
In housing construction project the main problem was material management system obstacle
to achieve the goal of housing. However, here was a problem of inefficient material
management and procurement, unnecessary material on site, delay material delivery,
inadequate material storage and poor material control on site.
In this study, construction material management can be viewed as four categories which
are assess the method of material procurement practices in construction projects, compare
the planned materials with the actual materials utilized Addis Ababa housing
construction projects, identify the mechanism of material management system in construction
projects and its challenges and identify the factors affecting effective material management
system.
The study was limited to Addis Ababa housing construction projects because it’s a
government project. Low cost houses built for the low income people and also the owners all
construction material suppliers by itself except sand supply by contractors.
Data collection was used including observation, documentation and questionnaire with
interviews. The structural questionnaire prepared based on literature review and seventy
questionnaires were distributed to the owners, consultants and contractors, fifty-five
questionnaires were received and analyzed.
The main result in this thesis material procurement was open bid and procures materials for
construction sites by head office provisions with site requisition; according to the three
parties all material used as per planned and also used some mechanism with challenges of
delivery at the wrong time which interrupted the work schedule and failure to order on time which delays the projects and factors affecting effectiveness of material management system
was inefficient work force
All parties interested in using some techniques of managing construction materials such as
creating and updating data base for materials price and provided listing of materials with
computerized form. The most challenges of material managements system was delivery at the
wrong time which interrupted the work schedule and failure to order on time which delays
the projects and factors affecting effectiveness of material management system was
inefficient work force.
A researcher recommends owner should be to develop human resource in construction
industry through proper and continuous training program about material management
system and should be create Awareness and accountability within the organization
Consultants should be awareness creation how to stacking and storage materials as per
specification for contractors
Contractors should ensure the use of skilled craftsmen for their works and provide efficient
supervision with professionals to ensure effective material management on building
construction sites