Abstract:
In many developing countries including Ethiopia water supply system has the problem of hydraulic
performance, water loss or leakage is the growing concern. Additionally, Disinfection By-Product is
another problem available in water treatment and distribution system. The objective of this study was
evaluating the performance of Naqamte town water distribution networks and treatment plant.
Hence, during this study, hydraulic performance, water loss in water distribution system, disinfection
and disinfection by-product was addressed. To evaluate the hydraulic performance of the water
distribution network, WaterGEMs V8i was adopted for water distribution modeling and for water
treatment plant simulation WatPro 4.0 software was applied for disinfection and treatment plant
performance. This study requires some tools, Geographical Position System and pressure gauge
meter that was used to collect the required elevation data, while Microsoft Excel sheet was also used
in organizing elevation data, and ArcGIS 10.3 was used to display the overlapped shape file of the
distribution network on the topographic map of the town. The study was involved both primary and
secondary data, the primary data was received from field surveying (pressure reading and
elevation). While the secondary data was collected from different newspaper, journals, related
books, literature reviews, design report, the town water supply service office existing documents and
annual. As per the analyzed results; the current maximum water demand in Naqamte town is
estimated at 12,345.36 m
3
/day, while small reservoirs capacity and low raw water pump efficiency
were observed in the town water distribution networks. As per the discussion held with the Naqamte
water supply and sewerage authority and field visit, the major factors of water loss was identified. As
per the calculation result; the treatment plant efficiency of the town was estimated as 69.75%. In
case of giardia and viruses reduction (22.6% and 75.34%), i.e. the results obtained from the
treatment plant simulation did not obey the surface water treatment rule. Despite its small amount;
disinfection by products has been found in the town’s water treatment plant. As per the calculation
obtained; the contact time of the water system did not met the contact time requirement because
0.476<1. In general, the current water distribution network and treatment plant of Naqamte town
was in poor performance and were not conducted adequate water to the various demand categories
of the town. Hence, it is important to rehabilitate and improve the water distribution network and
treatment plant of the town in order to fulfill the required need.