Abstract:
Construction industry is an industry, which is concerned within the Initiating, planning,
execution, Monitoring and controlling& Closing of all types of civil works. Now a days in
Ethiopia construction industries were booming due to implementing major infrastructure
projects together with many public buildings, Office building, Staff residential, High
school building construction project.
The study aims at identifying were to factors that affect monitoring and controlling
practices on public building construction in Jimma Zone from the view point of different
respondents including Clients, Consultants, Contractors, Regulatory and other who have
experience in public building construction and provides recommendations with reference
to handling of construction building. About 66 Factors were identified through literature
review and grouped into six groups. Respondents were required to rate how 66 factors of
project monitoring and controlling practices with respect to their importance.
The 6 groups of factors which have significant impact on the project monitoring and
controlling practices are ranked depending on their RII as: Communication Factor, Cost
Factor, Stakeholder engagement Factor, Schedule factors, Quality Factor and Scope
factor. According to the result of the study the top factors of project monitoring and
controlling practices includes: Price fluctuation, Shortage of material, Lack of
communication between parties, Inadequate design without site investigation, Cost
variations, Scope change within time, cost and quality change, Payment delay, Schedule
changes and Delays in decisions making.
The major impact lack of monitoring and controlling practices are time delay, cost
increase and quality factors from initial contract on this project are originated by the
employer, contractor, regulatory and consultant. The selected projects are comprises of
the completed three and one ongoing projects and those critically suffering by
abandonment and/or termination of the contract. Gatta high school, Sombo Dosha high
school and Kusaye high school are the completed projects and Ilke High school is under
construction projects.
It’s recommended that building construction organization assign project manager and
construction supervisors with sufficient management skills in project, minimize Accident
and any safety problems, develop human resources through proper and continuous
training programs frame a strong assignment, vision and a planned approach to
overcome poor project monitoring and controlling. It’s recommended that the
government should consider as major concern, to enforce hard and fast laws and
regulation that help to obtain practices work force in the building construction.