Abstract:
Time overrun considered as one of the most common problems causing a multitude negative effect on
projects, and its participating parties. Harar city is the ancient civilized city visited by tourists the living
museum in Ethiopia and this fact makes the necessity of standardized roads in the city even more critical
and vital. Despite this construction delay remains the main problem. This research is a cross-sectional
design in which data were collected at one time from respondents of the survey. The objective of the study
is to investigate the factors that cause time overrun during construction road construction projects of
Harar city. The total sample size of the study was 51 respondents from contracting companies, consultant
offices & client. The respondents’ documents were collected using questionnaire from client, contractors
and consultants. The questionnaire was cleared coded, and entered to statistical Software of Epi data
version 4.6 and exported into SPSS window version 26. Descriptive statistics was computed to determine
the frequency of variable. Relative Importance Index (RII) method were used to determine the relative
significance and ranking of the causes. Accordingly, except for contractor related factors (aggregate RII
0.47) all factors were significant by their aggregate relative importance index. The five most common
factors for road construction projects time overrun in Harrar city are Poor preparation and planning
(material/labor estimation) ((RII 0.861), Poor communication and coordination with other parties (RII
0.819), Escalation of material prices (RII 0.692), Slowness in making decisions (RII 0.676); Bureaucracy
in Government agencies (RII 0.657). The analysis carried out on the effect of time overrun in road
construction projects shows that extended completion time of the project (RII = 0.915), cost overrun (RII
= 0.879), disputes and claims (RII = 0.724), negative social impact (RII = 0.681) and arbitration (RII =
0.676) were ranked highest. However, the study identified ways that can be taken by construction
professionals and other stakeholders to avoid and eventually reduce time overrun in road construction
projects. Among other ways, the most suggested by respondents includes Effective strategic planning (RII
= 0.915), Proper site management and supervision (RII = 0.894), Proper project planning and scheduling
(RII = 0.892), Complete and proper design at the right time (RII = 0.890), Frequent progress meetings
(RII = 0.876), Accurate initial cost estimates (RII = 0.876) and Clear information and communication
channels (RII = 0.870).